The Day 90 Pre-Mortem Kit

Find what breaks before you sign.

Two tools. One hour with your frontline team, then 10 questions for the vendor. Use it on your next project, big or small. Print it, share it, steal it.

Derek O'Sullivan

Why I made this. I started out designing container cranes at Liebherr, and I've sat on both sides of the table since: buying systems, selling them, rolling them out. I have the scars from not getting the frontline involved early enough. This is the hour I wish we'd spent before signing. – Derek O'Sullivan

Why bother

Every failed rollout gets a post-mortem. Almost none gets a pre-mortem.

Gartner found that 76% of logistics transformations fail to meet critical performance metrics. Afterwards, everyone can explain what went wrong. The trick is getting those explanations before you sign, from the people who'll live with the system.

A pre-mortem does that. You imagine the project has already failed, then work out why. The psychologist Gary Klein wrote it up in Harvard Business Review back in 2007: people keep their doubts to themselves while a plan is being made, but once it has "failed", it's easy to be honest.

Part 1

The one-hour pre-mortem

Run it before you sign, or before go-live if you've already signed. It costs an hour and nothing else.

Who's in the room

6 to 10 people who'll live with the system: a checker, a dispatcher, a yard or warehouse planner, someone from IT, someone from finance. Not just the project sponsor.

Who runs it

Someone neutral. Not the sponsor, and not the person who picked the vendor.

What you need

Paper, pens, a wall or whiteboard, and one hour with phones away.

0–5 min

Set the scene

Read this out, word for word:

"It's Day 90. This has gone badly. What happened?"
5–10 min

Write in silence

Everyone writes down every reason they can think of, on paper, alone. No talking. This stops the most senior person setting the answer in the first thirty seconds.

10–30 min

Go round the room

One reason per person per round, until everyone runs out. Write each one on the wall. No debating and no "that won't happen".

30–45 min

Group and vote

Cluster the reasons that overlap. Everyone gets three votes. Circle the top five.

45–60 min

Turn risks into actions

For each of the top five, agree three things: who owns it, what question it raises for the vendor, and what test would prove it's handled before go-live.

House rules: the most senior person speaks last. Every reason counts. Write it down, don't defend it. Photograph the wall and look at it again at Day 30, 60 and 90.

Worked example

What a top five can look like

Illustrative only: a container terminal about to replace its terminal operating system (TOS). Yours will be different, which is the point.

Risk the room raisedOwnerQuestion for the vendorTest before go-live
A box grounded outside its planned slot disappears from the systemYard planner"What happens to a box that isn't where the system expects it?"Misplace 20 boxes on purpose in the test yard and find them
Gate, quay, yard and rail pass testing alone but jam when run togetherOps manager"Show me an integrated test at our peak-day volume"Full-day simulation with every area live at once
Hauliers and agents can't log in on day oneCustomer service lead"Who sets up our external users, and by when?"Every haulier and agent logged in and booking a week before cutover
Dirty data from the old system breaks planningIT lead"What has to be true about our data, and who cleans it?"Migrate a full copy, reconcile every box, fix before cutover
Productivity drops and there's no slack to absorb itTerminal manager"What dip should we plan for in month one?"Agree extra crews and temporary capacity for weeks 1 to 6

Part 2

10 questions to put to any vendor before you sign

Take your top five risks from Part 1 into the meeting, then add these. Swap the polite questions for proper ones.

  1. "Show me a customer like us at Day 90. What broke, and what did it take to fix?"Then ask to speak to that customer without the vendor on the call.
  2. "Which of our existing systems have you connected to live, not in a demo? Who can I call?"Integration is where most rollouts bleed.
  3. "What was tested on its own, and what was tested together, at our real volumes?"At Felixstowe in 2018, areas that passed testing separately failed when run together.
  4. "What has to be true about our data for this to work? What happens when it isn't?"Get them to name the data they're assuming you have.
  5. "If go-live goes wrong, what's the rollback plan, and how fast can we fall back?""It won't go wrong" is not a plan.
  6. "Who from your side is on site in the first 90 days, and who pays for their time?"Names, not roles.
  7. "How long does training take for frontline staff, and what productivity dip should we plan for in month one?"There's always a dip. The honest vendors will tell you how big.
  8. "What will cost extra after we sign?"Interfaces, customisation, change requests, support tiers, extra users.
  9. "What happens, contractually, if the agreed KPIs aren't met at Day 90?"If there's nothing in the contract, there's nothing.
  10. "What on your roadmap in the next 18 months could change or drop something we rely on?"You're buying the next three years, not the demo.

Watch how they answer, not just what they say. Specifics, names and numbers are good signs. "That's never happened" is an answer to worry about.

Part 3

The Day 30, 60 and 90 check-in

Signing is half the job. Book three 30-minute check-ins with the same people who were in the room, put the photo of the wall up, and ask the same questions each time.

WhenAsk
Every timeWhich of our top five risks happened, which didn't, and which ones did we miss? What manual workarounds are people using that the system should handle? How many defects are still open, and which one hurts most?
Day 30Is everyone who needs access actually using it, inside and outside the company? Where is training still falling short?
Day 60Are throughput and accuracy back to where they were before go-live? What did the vendor promise in week one that hasn't landed yet?
Day 90Are we hitting the KPIs in the contract? If the frontline team could choose again tomorrow, would they keep it?

Tip: write the answers down and send them to the vendor after each check-in. It turns "how's it going?" into a record, and the Day 90 one is the conversation the contract was written for.